Thor Impex started the construction of Wind Park Bogoslovec in early July 2021. As of June 2022, the following tasks are now completed or ongoing.
- Substations works
- Road works
- Cable works for overhead line
- Concreting works (half way) .
Further progress photos can be found on our Facebook page. “Wind Park Bogoslovec Macedonia
For the next 3 months the following work will take place
- Finalize concrete pouring for the foundations of the wind turbines in preparation for turbine delivery in August 2022.
- Prepare access from State Road for delivery of wind turbine components
Concrete pour works will continue to see increased levels of cement trucks on public roads to the site. Road users may experience some disruption, please follow any signage and take care when driving or walking along the road during this time. Be aware of the increased traffic.
If there are any concerns regarding the conduct of drivers/workers or any unsafe driving, incidents, property damage or other issues, please get in touch with the project using the details provided here.